January 2022
Developing Bid Ready Drawings
Architects have been tasked to develop bid ready drawings. Anticipate bid packages to be made available this summer.
October 2020

Booker Property Cleared
GVFRS has cleared the 3 building from the booker property in preparation of building the new station.
May 2020

Concept Design
A Concept design with multiple options has been submitted and is under review
January 2017

GVFRS identifies need to upgrade the station on Main Street
GVFRS has identified a need to update/upgrade the fire station on Main Street. The aging building has been added on to numerous times in the last 50+ years and can no longer support fire and EMS operations. A committee has been formed to develop options.